SARATOGA SPRINGS — Officials with the city’s Department of Public Works have announced a milling and paving project for Leaward Way and Ingersoll Road beginning on Monday, May 6.

The project schedule is currently as follows: 

Monday, May 6: Milling of Leaward Way from Timber Lane to the cul-de-sac

Tuesday, May 7: Milling of Ingersoll Road from Old Schuylerville Road to Azalea Drive

Wednesday, May 8: Paving of Leaward Way from Timber Land to the cul-de-sac

Thursday, May 9, and Friday, May 10: Paving of Ingersoll Road from Old Schuylerville Road to Azalea Drive. 

Please note that construction circumstances and/or weather conditions may prompt officials to revise this schedule. 

Milling and paving operations are scheduled to begin at 6 a.m. and wrap up around 2 p.m. daily.

On-street parking will be prohibited and driveway access may be limited with potentially lengthy delays during these times. 